PROJECTS

Rivulon Building 2

900 LF of 120” storage tanks, also included full water, fire and sewer system.

a

Mathison Tri Gas

1/2 mile of excavation and trenching to install SRP racked duct bank.

Southwest Airlines

Installation of 50,000 gallon storm water tank at Phoenix Sky Harbor Airport. Scope of work, also included a lift station, 3200 gallon oil water separator, R&R of asphalt and concrete and haul off of extra spoils.

Gilbert Temple

Project included 16” water main realignment in the middle of Pecos Road at night 3,200 linear feet of water and fire lines.